Basic Horizontal Info

Investigation of technical issues on HVDC transmission options Vs HVAC options and work together with SwedPower consultant (Sweden) and Teshmont consultant (Canada) for 1200 MW Hydro options from Sarawak to Sabah for a distant of over 600km. Load flow studies, Transient stability study, small signal stability studies, subsynchronous torsional oscillation study, and equipment design studies were included.